|
Project Schedule
March 2006
Engineering / Civil Surveys
April 2006
FERC Pre-Filing
July 2006
Public Meetings
December 2006
FERC Filing
September 2007
Receive FERC Certificate
December 2007
Begin Construction
September 2008
Pipeline
In-Service
January 2009
Compressor Sation
In-Service
News & Announcements

Project
Newsletter (5,400 KB) |

Gulfstream has reached an agreement with Progress
Energy to provide 155,000 dekatherms per day of natural gas
transportation service to serve Progress's Bartow Power Plant in
Pinellas County, Fla. This pipeline project is known as Gulfstream's
Phase IV expansion. The project will involve construction of approximately
17.8 miles of 20-inch pipeline in Tampa Bay connecting the existing
Gulfstream pipeline to the Bartow Power Plant. The project will
also require the installation of additional compression in Coden,
Ala., and Manatee County, Fla.
______________________________________________________________
CONSTRUCTION UPDATE
May 1, 2008 -- Offshore construction continues. The pipe lay barge and directional drilling barge are working in Tampa Bay.
   
  
______________________________________________________________
PROJECT OVERVIEW
Power Plant Modifications
Progress Energy has
announced plans to modify its Bartow Power Plant site in Pinellas
County to re-power its existing oil-fired generation capacity with
cleaner-burning natural gas-fired generation capacity. The conversion
is estimated to reduce emissions of sulfur dioxide, nitrogen oxides
and particulates by more than 90 percent.
Proposed Route
The proposed route extends approximately 17.8 miles from the existing
Gulfstream pipeline in the vicinity of Port Manatee north across
the middle bay to the existing Bartow Power Plant on the east shore
of St. Petersburg. Gulfstream is committed to working with appropriate
environmental agencies to identify a route that ensures the least
environmental disturbance.
Sub-sea Survey
In early 2006 Gulfstream researchers surveyed a 1,000 foot-wide
corridor in Tampa Bay to examine the seafloor for hard-bottoms,
submerged aquatic vegetation, archeological points of interest and
potential construction hazards. The data generated from these surveys
has helped Gulfstream identify environmentally sensitive areas to
be avoided for planning the proposed pipeline route. Surveys were
conducted using magnetometer, side scan sonar, sub-bottom profiler,
and echo sounder technology.
Construction Methods
Offshore construction will consist of two primary construction methods:
- Horizontal directional drilling - This technology will
enable Gulfstream to avoid sensitive environmental areas and also
cross existing waterways (or channels), while burying the pipe
at depths greater than could be achieved with traditional trenching.
Gulfstream is planning at least five of these drills.
- Pipe-lay barge - A shallow-water pipe-lay barge will
be used during the 8-month offshore construction process.

Environmental Commitment
- The proposed route minimizes impacts within Pinellas County
Aquatic Preserve by avoidance and directional drilling.
- The pipeline route will avoid soft and hard live-bottoms and
sea grasses almost entirely.
- Manatee spotters will monitor for the presence of manatees and
other critical species during construction.
- Once Phase IV is in operation and the Bartow Plant is repowered
to use natural gas instead of oil.
- Sulfur dioxide, nitrogen oxides and particulate emissions from
the plant will be reduced more than 90% from present levels.
Manatee County Compressor
Facility
The project will include construction of a 30,000-hp natural gas
pipeline compressor facility in
Manatee County, Fla. Gulfstream's objective is to site the facility
on a location that minimizes residential and environmental impacts.
The company is evaluating one location in an industrial area of
northwestern Manatee County -- an 80-acre tract located north of
Buckeye Road, east of the Piney Point Phosphate Plant.
Siting Criteria
There are a number of factors that must be taken into consideration
when choosing suitable location for a compressor facility. Some
of the factors that must be considered include local zoning restrictions
and physical constraints such as:
- Proximity to existing pipeline
- Access to electric power
- Pipeline hydraulics
- Compatible with zoning, land use
- Site terrain
- Water table & storm water
- Site accessibility
The pipeline company must also evaluate a number of environmental
factors, including potential impacts on:
- Residents
- Threatened & endangered species
- Wetlands, water bodies & groundwater
- Fish, vegetation and other wildlife
- Cultural resources
- Geology
- Soils
- Land use
- Air and noise quality
Compressor Facilities
Compressor stations, sometimes called pumping stations, are the
"engine" that powers aninterstate natural gas pipeline.
Most compressor stations are completely automated, so the equipment
can be started or stopped from a pipeline's central control room.
The control center also can remotely operate shut-off valves along
the transmission system. The operators of the system keep detailed
operating data on each compressor station, and continuously adjust
the mix of engines that are running to maximize efficiency and safety.
Safety Features
The proposed facility will be operated in accordance with all applicable
safety standards established by the U.S. Department of Transportation's
Pipeline and Hazardous Materials Safety Administration. Some of
those safety features include:
- Continuously monitored 24 hours a day / 365 days a year from
Gas Control Center.
- Automation system allows compressors to be started, controlled
and stopped remotely at any time.
- Automation system protects the facility & surrounding area
if equipment is not operating correctly.
- Remotely operated station shut-off valves.
- Extensive emergency systems include sophisticated sensors to
detect leaks or fire.
Regulatory Process
The
Federal Energy Regulatory Commission (FERC) is charged by Congress
with determiningwhether or not proposed interstate pipeline projects
are in the public convenience and necessity. The information below
explains the FERC's review process for the planned project, and
how you can get involved in the process.
FERC Pre-Filing
On April 26, 2006, Gulfstream requested the Federal Energy Regulatory
Commission (FERC) initiate an environmental review of Phase IV Expansion
Project prior to the company's certificate application. This process,
known as pre-filing, is facilitated by the FERC to encourage involvement
by citizens, government entities and other interested parties in
the very early design stages of a proposed project. 
During the pre-filing process, the FERC notifies citizens, government
entities and other interested parties of the proposed project and
requests comments. Gulfstream hosted public workshops July 11, 12
& 13 to solicit feedback and gather comments related to the
project. Approximately 60 interested parties attended the workshops.
FERC Filing
Gulfstream filed a certificate application with the FERC on December
22, 2006. The FERC assigned the project Docket Number CP07-51-000.
The FERC approved the project in September 2007. All documents and correspondence submitted to or issued by the FERC
regarding the Phase IV Expansion Project can be accessed by referencing
the Docket Number on the FERC website located at http://elibrary.ferc.gov/idmws/search/fercgensearch.asp.
Environmental Assessment (EA)
The FERC will prepare an EA using information included in Gulfstream's
certificate application, supplemental information that may be provided
by Gulfstream upon request, and information assembled by its own
staff. The EA will describe the proposed project and alternatives
and will identify existing environmental conditions and the potential
impacts from the project. The EA will also indicate what mitigation
measures, construction procedures, and routing could be included
in the project to eliminate or reduce impacts.
Once the EA is issued, stakeholders will have a 30-day period to
comment.
Certificate of Public Need and Necessity
In September 2007 the FERC issued an Order granting a Certificate of Public Convenience
and Necessity. This is the document FERC issues that signifies the
approval has been granted to build and operate the pipeline. Comments
received on the EA are typically addressed by FERC in this document.
The certificate details the conditions of the approval, including
the final route that FERC has authorized, and construction and mitigation
measures that Gulfstream must follow.
Comments to FERC
When providing comments to the FERC, you should reference pre-filing
Docket No. CP07-51-000. Comments may be filed via the Internet on
the FERC's website at http://www.ferc.gov.
You may provide written comments to the FERC by sending them to:
Magalie R. Salas, Secretary
Federal Energy Regulatory Commission
888 First St., N.E., Room 1A
Washington, DC 20426
|